Omexom Especialistas and Omexom Barcelona are working on this project together.

 

This project encompasses various different tasks carried out at a sub-station owned by Red Eléctrica de España in Santa Coloma for a total of €1,700,000. They involve replacing a switchyard for another indoor SF6 insulated one, with the sub-station in operation. With regard to electro-mechanics, the switchgear will be dismantled and subsequently reassembled inside, including all the building’s general services. In terms of civil engineering, all the foundations will be demolished and new ones built, along with the piping and accesses to the building.